View completed phase

Phase 2 Current phase

Exploration phase 2024 - 2027

    Defining possible solutions

    Winter & Spring 2025
    Nederland

    We will explore possible solutions to improve the rail network. We will also use the input we received during the first information meetings for this purpose. In the Netherlands, we will describe the results in the Memorandum on Scope and Level of Detail.

    België

    In Flanders, we will describe the same possible solutions in the scoping note.

    Information meetings

    Summer 2025
    Nederland België

    We will present the possible solutions, based on the research we carried out over the past six months.

    Selecting promising solutions

    Autumn 2025
    Nederland België

    We will process the input from the information meetings/consultations. We will subsuquently choose the most promising solutions. The same promising solutions will be selected in Flanders and the Netherlands.

    Information meetings

    Autumn 2025
    Nederland België

    During the information meetings, we will explain which solutions are most promising and why. We will also outline the procedure going forward.

    Environmental impact study

    Winter & Spring 2026
    Nederland België

    We will examine the environmental impacts of the preferred solutions. We will record the results in the EIR plan. There will be one EIR plan for both Flanders and the Netherlands.

    Choosing the best solution

    Spring 2026
    Nederland

    We will choose the best solution after a comprehensive assessment. We will for instance consider environmental impacts and feasibility. This information will be included in the Draft Preferred Decision.

    België

    The same information will be included in Flanders in the preliminary draft SIP, including draft EIR plan.

    Information meetings

    Spring 2026
    Nederland België

    We will explain what the best solution is, explain the plan EIA, and explain how the procedures will proceed.

    Stakeholder advice

    2027
    Nederland België

    The plan is open for inspection in the Netherlands and a Public Inquiry will take place in Flanders. Stakeholders can give their opinions on the plan before it is finalised. The opinions received will then be processed and, where necessary, the plan can be adapted accordingly.

    End of exploration phase

    Expected by end of 2027
    Nederland

    The exploration phase ends when the minister adopts the Preferential Decision.  

    België

    The exploration phase ends when the Flemish government definitively adopts the Spatial Implementation Plan (SIP).

Phase 3

Plan development and realisation, vanaf 2028

    Start of plan development and realisation

    Expected 2028
    Nederland België

    We will further develop the best solution. In this phase, we will draw up detailed plans, purchase the land needed, submit environmental permit applications (Belgium), and proceed with planning procedures in the Netherlands. We will then look for contractors for the project. After this realisation starts.

Phase 1

Pre-exploration 2017 - 2024

    Preliminary studies

    2017-2020
    Nederland België

    In 2017 it became clear that freight rail bottlenecks would arise in the future if no action is taken. Eleven different preliminary studies were eventually conducted on the bottlenecks in the current rail network. 

    Letter of Intent

    2021
    Nederland België

    Several Dutch and Belgian governments signed a letter of intent for further exploration and plan development.

    Start of project organisation

    2023
    Nederland België

    To further explore possible rail developments, North Sea Port, Infrabel, and ProRail teamed up as Rail Ghent Terneuzen project organisation.

    European grant

    2023
    Nederland België

    The EU provided a € 3.4m CEF grant to highlight the importance of sustainable, cross-border rail development.

Phase 2

Exploration phase 2024 - 2027

    Start of exploration phase

    Autumn 2024
    Nederland

    If the ministry approves ProRail's plan, the exploration phase will start in the Netherlands. We will then publish the kick-off and the participation plan

    België

    The Flemish government, together with Infrabel, will make a plan for the exploration. After the plan is approved, the exploration phase starts in Flanders. We will then publish the start note and process note.

    Information meetings

    Autumn 2024
    Nederland België

    During the information meetings/consultations, we will explain how the exploration phase will proceed and how we will involve the community. 

Go to current phase